851 lines
23 KiB
Markdown
851 lines
23 KiB
Markdown
|
|
# Master Task List - Complete Overview
|
||
|
|
|
||
|
|
## 📋 All Remaining Tasks
|
||
|
|
|
||
|
|
### Category 1: CCIPLogger Deployment (2 tasks)
|
||
|
|
|
||
|
|
#### Task 1.1: Fix Hardhat Dependency Resolution
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-4 hours
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Check Hardhat configuration for path resolution
|
||
|
|
- Verify node_modules structure
|
||
|
|
- Try alternative installation methods (npm link, direct path)
|
||
|
|
- Consider using Hardhat's resolver configuration
|
||
|
|
- Test with `npx hardhat compile --show-stack-traces` for detailed errors
|
||
|
|
- **Recommendations**:
|
||
|
|
- Try `npm install --legacy-peer-deps --force`
|
||
|
|
- Use `yarn` instead of `npm`
|
||
|
|
- Install in a fresh node_modules directory
|
||
|
|
- Use npm workspaces
|
||
|
|
- Consider Remix IDE as backup deployment method
|
||
|
|
- **Success Criteria**: Hardhat can compile CCIPLogger contract
|
||
|
|
|
||
|
|
#### Task 1.2: Deploy CCIPLogger to Mainnet
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 hours
|
||
|
|
- **Dependencies**: Task 1.1
|
||
|
|
- **Description**:
|
||
|
|
- Compile contract successfully
|
||
|
|
- Deploy to Ethereum Mainnet
|
||
|
|
- Verify contract on Etherscan
|
||
|
|
- Update .env with deployed address
|
||
|
|
- Test contract functions
|
||
|
|
- **Recommendations**:
|
||
|
|
- Use multisig for deployment
|
||
|
|
- Verify constructor parameters
|
||
|
|
- Test contract after deployment
|
||
|
|
- **Success Criteria**: CCIPLogger deployed and verified on Etherscan
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 2: Chain-138 Infrastructure (2 tasks)
|
||
|
|
|
||
|
|
#### Task 2.1: Verify Chain-138 Infrastructure
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Verify Chain-138 RPC endpoint is accessible
|
||
|
|
- Confirm Chain-138 CCIP Router address
|
||
|
|
- Verify Chain-138 chain selector (0x000000000000008a)
|
||
|
|
- Ensure wallet has sufficient native tokens on Chain-138
|
||
|
|
- Verify Chain-138 network is operational
|
||
|
|
- **Recommendations**:
|
||
|
|
- Set up backup RPC endpoints
|
||
|
|
- Monitor RPC uptime
|
||
|
|
- Use multiple RPC providers
|
||
|
|
- **Success Criteria**: All infrastructure verified and accessible
|
||
|
|
|
||
|
|
#### Task 2.2: Configure Chain-138 CCIP Router
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 hours
|
||
|
|
- **Dependencies**: Task 2.1
|
||
|
|
- **Description**:
|
||
|
|
- Identify Chain-138 CCIP Router address
|
||
|
|
- Verify router is deployed and operational
|
||
|
|
- Check router supports required functions
|
||
|
|
- Update .env with CCIP_ROUTER for Chain-138
|
||
|
|
- Test router connectivity
|
||
|
|
- **Recommendations**:
|
||
|
|
- Check Chainlink CCIP Directory for official router
|
||
|
|
- Verify router compatibility
|
||
|
|
- Test router functions
|
||
|
|
- **Success Criteria**: CCIP Router configured and tested
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 3: Chain-138 Bridge Deployment (2 tasks)
|
||
|
|
|
||
|
|
#### Task 3.1: Deploy CCIPWETH9Bridge on Chain-138
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 hours
|
||
|
|
- **Dependencies**: Tasks 2.1, 2.2
|
||
|
|
- **Description**:
|
||
|
|
- Run `./scripts/deployment/deploy-bridges-chain138.sh`
|
||
|
|
- Deploy CCIPWETH9Bridge
|
||
|
|
- Verify deployment on-chain
|
||
|
|
- Update .env with Chain-138 bridge address
|
||
|
|
- Verify bridge contract is functional
|
||
|
|
- **Recommendations**:
|
||
|
|
- Use multisig for deployment
|
||
|
|
- Verify constructor parameters
|
||
|
|
- Test bridge functions after deployment
|
||
|
|
- **Success Criteria**: CCIPWETH9Bridge deployed and verified on Chain-138
|
||
|
|
|
||
|
|
#### Task 3.2: Deploy CCIPWETH10Bridge on Chain-138
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 hours
|
||
|
|
- **Dependencies**: Tasks 2.1, 2.2
|
||
|
|
- **Description**:
|
||
|
|
- Deploy CCIPWETH10Bridge
|
||
|
|
- Verify deployment on-chain
|
||
|
|
- Update .env with Chain-138 bridge address
|
||
|
|
- Verify bridge contract is functional
|
||
|
|
- **Recommendations**:
|
||
|
|
- Use multisig for deployment
|
||
|
|
- Verify constructor parameters
|
||
|
|
- Test bridge functions after deployment
|
||
|
|
- **Success Criteria**: CCIPWETH10Bridge deployed and verified on Chain-138
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 4: Bridge Configuration (3 tasks)
|
||
|
|
|
||
|
|
#### Task 4.1: Configure WETH9 Bridge Destinations
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1 hour
|
||
|
|
- **Dependencies**: Tasks 3.1, 3.2
|
||
|
|
- **Description**:
|
||
|
|
- Add Chain-138 destination to Mainnet WETH9 bridge
|
||
|
|
- Add Mainnet destination to Chain-138 WETH9 bridge
|
||
|
|
- Enable destinations on both bridges
|
||
|
|
- Verify configuration on-chain
|
||
|
|
- Test destination retrieval
|
||
|
|
- **Recommendations**:
|
||
|
|
- Use multisig for configuration
|
||
|
|
- Test with small amounts first
|
||
|
|
- Monitor configuration transactions
|
||
|
|
- **Success Criteria**: WETH9 bridge destinations configured and verified
|
||
|
|
|
||
|
|
#### Task 4.2: Configure WETH10 Bridge Destinations
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1 hour
|
||
|
|
- **Dependencies**: Tasks 3.1, 3.2
|
||
|
|
- **Description**:
|
||
|
|
- Add Chain-138 destination to Mainnet WETH10 bridge
|
||
|
|
- Add Mainnet destination to Chain-138 WETH10 bridge
|
||
|
|
- Enable destinations on both bridges
|
||
|
|
- Verify configuration on-chain
|
||
|
|
- Test destination retrieval
|
||
|
|
- **Recommendations**:
|
||
|
|
- Use multisig for configuration
|
||
|
|
- Test with small amounts first
|
||
|
|
- Monitor configuration transactions
|
||
|
|
- **Success Criteria**: WETH10 bridge destinations configured and verified
|
||
|
|
|
||
|
|
#### Task 4.3: Verify Bridge Configuration
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 30 minutes
|
||
|
|
- **Dependencies**: Tasks 4.1, 4.2
|
||
|
|
- **Description**:
|
||
|
|
- Verify all destinations are configured correctly
|
||
|
|
- Test destination queries
|
||
|
|
- Verify destination enablement status
|
||
|
|
- Document configuration
|
||
|
|
- **Success Criteria**: All bridge configurations verified and documented
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 5: Testing (5 tasks)
|
||
|
|
|
||
|
|
#### Task 5.1: Pre-Testing Setup
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 hours
|
||
|
|
- **Dependencies**: Tasks 4.1, 4.2, 4.3
|
||
|
|
- **Description**:
|
||
|
|
- Ensure bridges are configured
|
||
|
|
- Fund test wallet with WETH9 on Mainnet
|
||
|
|
- Fund test wallet with native tokens on both chains
|
||
|
|
- Fund bridges with LINK for CCIP fees
|
||
|
|
- Verify CCIP Router connectivity
|
||
|
|
- **Success Criteria**: All pre-testing requirements met
|
||
|
|
|
||
|
|
#### Task 5.2: Test WETH9 Cross-Chain Transfers
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: Task 5.1
|
||
|
|
- **Description**:
|
||
|
|
- Test Mainnet → Chain-138 transfer
|
||
|
|
- Verify WETH9 approval
|
||
|
|
- Verify CCIP message sent
|
||
|
|
- Monitor CCIP message delivery
|
||
|
|
- Verify WETH9 received on Chain-138
|
||
|
|
- Test Chain-138 → Mainnet transfer
|
||
|
|
- Verify reverse transfer works
|
||
|
|
- **Success Criteria**: Both directions tested and verified
|
||
|
|
|
||
|
|
#### Task 5.3: Test WETH10 Cross-Chain Transfers
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: Task 5.1
|
||
|
|
- **Description**:
|
||
|
|
- Test Mainnet → Chain-138 transfer
|
||
|
|
- Verify WETH10 approval
|
||
|
|
- Verify CCIP message sent
|
||
|
|
- Monitor CCIP message delivery
|
||
|
|
- Verify WETH10 received on Chain-138
|
||
|
|
- Test Chain-138 → Mainnet transfer
|
||
|
|
- Verify reverse transfer works
|
||
|
|
- **Success Criteria**: Both directions tested and verified
|
||
|
|
|
||
|
|
#### Task 5.4: Edge Case Testing
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 3-4 hours
|
||
|
|
- **Dependencies**: Tasks 5.2, 5.3
|
||
|
|
- **Description**:
|
||
|
|
- Test with minimum amounts
|
||
|
|
- Test with maximum amounts (if applicable)
|
||
|
|
- Test failed transfers
|
||
|
|
- Test replay protection
|
||
|
|
- Test with insufficient LINK for fees
|
||
|
|
- Test with insufficient WETH balance
|
||
|
|
- **Success Criteria**: All edge cases tested and documented
|
||
|
|
|
||
|
|
#### Task 5.5: Performance Testing
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: Tasks 5.2, 5.3
|
||
|
|
- **Description**:
|
||
|
|
- Measure transfer times
|
||
|
|
- Monitor gas costs
|
||
|
|
- Test batch transfers (if supported)
|
||
|
|
- Load testing (if applicable)
|
||
|
|
- **Success Criteria**: Performance benchmarks established
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 6: Monitoring (6 tasks)
|
||
|
|
|
||
|
|
#### Task 6.1: Set Up Etherscan Alerts
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 hours
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Set up Etherscan account
|
||
|
|
- Configure contract watch lists
|
||
|
|
- Set up transaction alerts
|
||
|
|
- Configure event alerts
|
||
|
|
- Set up balance alerts
|
||
|
|
- **Success Criteria**: All Etherscan alerts configured
|
||
|
|
|
||
|
|
#### Task 6.2: Set Up Event Monitoring
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 3-4 hours
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Set up event indexer (The Graph, Alchemy, etc.)
|
||
|
|
- Monitor CrossChainTransferInitiated events
|
||
|
|
- Monitor CrossChainTransferCompleted events
|
||
|
|
- Monitor CrossChainTransferFailed events
|
||
|
|
- Monitor RemoteTxLogged events (CCIPLogger)
|
||
|
|
- Monitor RemoteBatchLogged events (CCIPLogger)
|
||
|
|
- **Success Criteria**: Event monitoring operational
|
||
|
|
|
||
|
|
#### Task 6.3: Set Up Balance Monitoring
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Set up bridge LINK balance monitoring
|
||
|
|
- Set up bridge WETH balance monitoring
|
||
|
|
- Configure low balance alerts
|
||
|
|
- Set up automatic refill scripts (optional)
|
||
|
|
- Monitor wallet balances
|
||
|
|
- **Success Criteria**: Balance monitoring operational
|
||
|
|
|
||
|
|
#### Task 6.4: Set Up CCIP Message Tracking
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Set up CCIP Explorer monitoring
|
||
|
|
- Monitor message status
|
||
|
|
- Track message delivery times
|
||
|
|
- Alert on failed messages
|
||
|
|
- Track message costs
|
||
|
|
- **Success Criteria**: CCIP message tracking operational
|
||
|
|
|
||
|
|
#### Task 6.5: Create Monitoring Dashboard
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 4-6 hours
|
||
|
|
- **Dependencies**: Tasks 6.1, 6.2, 6.3, 6.4
|
||
|
|
- **Description**:
|
||
|
|
- Create monitoring dashboard
|
||
|
|
- Display contract statuses
|
||
|
|
- Show recent transfers
|
||
|
|
- Display balance information
|
||
|
|
- Show CCIP message status
|
||
|
|
- **Success Criteria**: Dashboard operational
|
||
|
|
|
||
|
|
#### Task 6.6: Configure Alerting
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 hours
|
||
|
|
- **Dependencies**: Tasks 6.1, 6.2, 6.3, 6.4
|
||
|
|
- **Description**:
|
||
|
|
- Set up email alerts
|
||
|
|
- Set up Slack/Discord notifications
|
||
|
|
- Configure PagerDuty (if needed)
|
||
|
|
- Set alert thresholds
|
||
|
|
- Test alert system
|
||
|
|
- **Success Criteria**: Alerting system operational and tested
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 7: Security (1 task)
|
||
|
|
|
||
|
|
#### Task 7.1: Security Review
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 8-12 hours
|
||
|
|
- **Dependencies**: All deployment tasks
|
||
|
|
- **Description**:
|
||
|
|
- Use multisig for admin functions
|
||
|
|
- Review access controls
|
||
|
|
- Verify replay protection
|
||
|
|
- Consider professional audit
|
||
|
|
- Document security measures
|
||
|
|
- **Recommendations**:
|
||
|
|
- Professional security audit recommended
|
||
|
|
- Review all access controls
|
||
|
|
- Test security measures
|
||
|
|
- **Success Criteria**: Security review completed
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 8: Documentation (1 task)
|
||
|
|
|
||
|
|
#### Task 8.1: Update Documentation
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 4-6 hours
|
||
|
|
- **Dependencies**: All tasks
|
||
|
|
- **Description**:
|
||
|
|
- Update deployment procedures
|
||
|
|
- Create configuration guides
|
||
|
|
- Document testing procedures
|
||
|
|
- Create operational runbooks
|
||
|
|
- Update user documentation
|
||
|
|
- **Success Criteria**: All documentation updated
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 9: Optimization (1 task)
|
||
|
|
|
||
|
|
#### Task 9.1: Gas Optimization
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 4-6 hours
|
||
|
|
- **Dependencies**: All deployment tasks
|
||
|
|
- **Description**:
|
||
|
|
- Review gas usage
|
||
|
|
- Implement batching where possible
|
||
|
|
- Optimize CCIP fee management
|
||
|
|
- Monitor and optimize costs
|
||
|
|
- **Success Criteria**: Gas usage optimized
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## 🎯 Priority Summary
|
||
|
|
|
||
|
|
### Critical (Must Complete First)
|
||
|
|
1. Fix CCIPLogger deployment dependency
|
||
|
|
2. Verify Chain-138 infrastructure
|
||
|
|
3. Configure Chain-138 CCIP Router
|
||
|
|
4. Deploy Chain-138 bridges
|
||
|
|
5. Configure bridge destinations
|
||
|
|
6. Basic cross-chain testing
|
||
|
|
|
||
|
|
### High Priority (Important)
|
||
|
|
7. Comprehensive testing
|
||
|
|
8. Edge case testing
|
||
|
|
9. Monitoring setup
|
||
|
|
10. Alerting configuration
|
||
|
|
11. Security review
|
||
|
|
|
||
|
|
### Medium Priority (Nice to Have)
|
||
|
|
12. Performance testing
|
||
|
|
13. Dashboard creation
|
||
|
|
14. Documentation updates
|
||
|
|
15. Gas optimization
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## 📊 Task Dependencies Graph
|
||
|
|
|
||
|
|
```
|
||
|
|
CCIPLogger Deployment (1.1, 1.2)
|
||
|
|
↓
|
||
|
|
Chain-138 Infrastructure (2.1, 2.2)
|
||
|
|
↓
|
||
|
|
Chain-138 Bridge Deployment (3.1, 3.2)
|
||
|
|
↓
|
||
|
|
Bridge Configuration (4.1, 4.2, 4.3)
|
||
|
|
↓
|
||
|
|
Testing (5.1, 5.2, 5.3, 5.4, 5.5)
|
||
|
|
↓
|
||
|
|
Monitoring (6.1-6.6)
|
||
|
|
↓
|
||
|
|
Security Review (7.1)
|
||
|
|
↓
|
||
|
|
Documentation (8.1)
|
||
|
|
↓
|
||
|
|
Optimization (9.1)
|
||
|
|
```
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## ⏱️ Time Estimates
|
||
|
|
|
||
|
|
- **Critical Path**: 1-2 weeks
|
||
|
|
- **High Priority**: 2-3 weeks
|
||
|
|
- **Complete**: 3-4 weeks
|
||
|
|
- **Production Ready**: 4-6 weeks
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## 🚨 Risk Assessment
|
||
|
|
|
||
|
|
### High Risk
|
||
|
|
- CCIPLogger dependency resolution
|
||
|
|
- Chain-138 infrastructure availability
|
||
|
|
- Cross-chain transfer reliability
|
||
|
|
|
||
|
|
### Medium Risk
|
||
|
|
- Bridge configuration errors
|
||
|
|
- Testing gaps
|
||
|
|
- Monitoring setup
|
||
|
|
|
||
|
|
### Low Risk
|
||
|
|
- Documentation
|
||
|
|
- Optimization
|
||
|
|
- Dashboard creation
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## ✅ Success Criteria
|
||
|
|
|
||
|
|
### Deployment Complete
|
||
|
|
- All contracts deployed and verified
|
||
|
|
- All configurations complete
|
||
|
|
- Basic testing passed
|
||
|
|
|
||
|
|
### Production Ready
|
||
|
|
- Comprehensive testing completed
|
||
|
|
- Monitoring operational
|
||
|
|
- Documentation complete
|
||
|
|
- Security review passed
|
||
|
|
- Operational procedures documented
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## 🏢 Enterprise Architecture Tasks (20 New Tasks)
|
||
|
|
|
||
|
|
### Category 10: ERC-2535 Diamond Implementation (2 tasks)
|
||
|
|
|
||
|
|
#### Task 10.1: Design Diamond Architecture
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 weeks
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Define facet structure and organization
|
||
|
|
- Design upgrade mechanisms
|
||
|
|
- Plan access control system
|
||
|
|
- Design facet management system
|
||
|
|
- Create architecture diagrams
|
||
|
|
- **Deliverables**:
|
||
|
|
- Architecture design document
|
||
|
|
- Facet structure diagram
|
||
|
|
- Upgrade mechanism specification
|
||
|
|
- Access control design
|
||
|
|
- **Success Criteria**: Complete architecture design approved
|
||
|
|
|
||
|
|
#### Task 10.2: Implement ERC-2535 Diamond Core
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.1
|
||
|
|
- **Description**:
|
||
|
|
- Deploy Diamond hub contract
|
||
|
|
- Implement facet management
|
||
|
|
- Set up upgrade controls
|
||
|
|
- Implement access control
|
||
|
|
- Test upgrade mechanisms
|
||
|
|
- **Deliverables**:
|
||
|
|
- Diamond hub contract
|
||
|
|
- Facet management system
|
||
|
|
- Upgrade mechanism
|
||
|
|
- Access control system
|
||
|
|
- **Success Criteria**: Diamond hub deployed and tested
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 11: ERC Standards Facets (6 tasks)
|
||
|
|
|
||
|
|
#### Task 11.1: Implement ERC-20/ERC-777 Facet
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-20 standard
|
||
|
|
- Implement ERC-777 standard
|
||
|
|
- FireFly integration
|
||
|
|
- CCIP bridging support
|
||
|
|
- ISO 4217 currency mapping
|
||
|
|
- **Success Criteria**: ERC-20/777 facet operational
|
||
|
|
|
||
|
|
#### Task 11.2: Implement ERC-721/ERC-1155 Facet
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-721 standard
|
||
|
|
- Implement ERC-1155 standard
|
||
|
|
- FireFly asset management
|
||
|
|
- Fractionalized asset support
|
||
|
|
- CCIP bridging support
|
||
|
|
- **Success Criteria**: ERC-721/1155 facet operational
|
||
|
|
|
||
|
|
#### Task 11.3: Implement ERC-1400/ERC-1404 Facet
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-1400 standard
|
||
|
|
- Implement ERC-1404 standard
|
||
|
|
- Transfer restrictions
|
||
|
|
- Compliance features
|
||
|
|
- KYC/AML integration
|
||
|
|
- **Success Criteria**: ERC-1400/1404 facet operational
|
||
|
|
|
||
|
|
#### Task 11.4: Implement ERC-3475 Facet
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-3475 standard
|
||
|
|
- Bond issuance
|
||
|
|
- Tranche management
|
||
|
|
- Maturity tracking
|
||
|
|
- Interest calculations
|
||
|
|
- **Success Criteria**: ERC-3475 facet operational
|
||
|
|
|
||
|
|
#### Task 11.5: Implement ERC-3643 Facet
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-3643 standard
|
||
|
|
- KYC/AML compliance
|
||
|
|
- Identity verification
|
||
|
|
- Enterprise features
|
||
|
|
- Compliance checks
|
||
|
|
- **Success Criteria**: ERC-3643 facet operational
|
||
|
|
|
||
|
|
#### Task 11.6: Implement ERC-4626 Facet
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-4626 standard
|
||
|
|
- Vault operations
|
||
|
|
- Yield strategies
|
||
|
|
- Collateral management
|
||
|
|
- Lending protocols
|
||
|
|
- **Success Criteria**: ERC-4626 facet operational
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 12: ISO Standards Integration (2 tasks)
|
||
|
|
|
||
|
|
#### Task 12.1: Implement ISO Registry Contract
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Deploy Registry contract
|
||
|
|
- Implement ISO 20022 support
|
||
|
|
- Implement ISO 4217 support
|
||
|
|
- Implement ISO 8583 support
|
||
|
|
- Implement ISO 6166 support
|
||
|
|
- Implement ISO 17442 support
|
||
|
|
- **Success Criteria**: ISO Registry deployed and operational
|
||
|
|
|
||
|
|
#### Task 12.2: Set Up ISO Standards Mappings
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 weeks
|
||
|
|
- **Dependencies**: Task 12.1
|
||
|
|
- **Description**:
|
||
|
|
- Set up currency code mappings (ISO 4217)
|
||
|
|
- Set up securities identifier mappings (ISO 6166)
|
||
|
|
- Set up LEI mappings (ISO 17442)
|
||
|
|
- Set up payment code mappings (ISO 20022)
|
||
|
|
- Set up card messaging mappings (ISO 8583)
|
||
|
|
- Create off-chain metadata database
|
||
|
|
- **Success Criteria**: All ISO mappings operational
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 13: FireFly Integration (2 tasks)
|
||
|
|
|
||
|
|
#### Task 13.1: Deploy FireFly Infrastructure
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: None
|
||
|
|
- **Description**:
|
||
|
|
- Set up FireFly network
|
||
|
|
- Configure FireFly plugins
|
||
|
|
- Set up identity system
|
||
|
|
- Configure token plugin
|
||
|
|
- Test FireFly connectivity
|
||
|
|
- **Success Criteria**: FireFly infrastructure operational
|
||
|
|
|
||
|
|
#### Task 13.2: Implement FireFly Integration
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Tasks 10.2, 13.1
|
||
|
|
- **Description**:
|
||
|
|
- Implement private asset flows
|
||
|
|
- Implement token plugin integration
|
||
|
|
- Implement event orchestration
|
||
|
|
- Implement signature verification
|
||
|
|
- Test complete FireFly → Ethereum flow
|
||
|
|
- **Success Criteria**: FireFly fully integrated
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 14: Bridge & Vault Modules (2 tasks)
|
||
|
|
|
||
|
|
#### Task 14.1: Implement Diamond Bridge Module
|
||
|
|
- **Priority**: 🔴 Critical
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Tasks 10.2, 13.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement CCIP message handling
|
||
|
|
- Implement batch settlement
|
||
|
|
- Implement FireFly signature verification
|
||
|
|
- Implement state synchronization
|
||
|
|
- Test bridge functionality
|
||
|
|
- **Success Criteria**: Bridge module operational
|
||
|
|
|
||
|
|
#### Task 14.2: Implement Vault/Collateral Module
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Tasks 10.2, 11.6
|
||
|
|
- **Description**:
|
||
|
|
- Implement ERC-4626 compliance
|
||
|
|
- Implement yield strategies
|
||
|
|
- Implement collateral management
|
||
|
|
- Test vault operations
|
||
|
|
- **Success Criteria**: Vault module operational
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 15: Governance Module (1 task)
|
||
|
|
|
||
|
|
#### Task 15.1: Implement Governance/DAO Module
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: Task 10.2
|
||
|
|
- **Description**:
|
||
|
|
- Implement voting system
|
||
|
|
- Implement proposal management
|
||
|
|
- Implement FireFly integration
|
||
|
|
- Implement execution automation
|
||
|
|
- Test governance functions
|
||
|
|
- **Success Criteria**: Governance module operational
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 16: Enterprise Testing (3 tasks)
|
||
|
|
|
||
|
|
#### Task 16.1: Test All Diamond Facets
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: All facet tasks
|
||
|
|
- **Description**:
|
||
|
|
- Unit tests for each facet
|
||
|
|
- Integration tests
|
||
|
|
- Upgrade mechanism tests
|
||
|
|
- Access control tests
|
||
|
|
- **Success Criteria**: All facets tested and verified
|
||
|
|
|
||
|
|
#### Task 16.2: Test FireFly Integration
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 weeks
|
||
|
|
- **Dependencies**: Task 13.2
|
||
|
|
- **Description**:
|
||
|
|
- Test private flows
|
||
|
|
- Test signature verification
|
||
|
|
- Test event orchestration
|
||
|
|
- Test end-to-end flows
|
||
|
|
- **Success Criteria**: FireFly integration tested
|
||
|
|
|
||
|
|
#### Task 16.3: Test ISO Standards Integration
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 1-2 weeks
|
||
|
|
- **Dependencies**: Task 12.2
|
||
|
|
- **Description**:
|
||
|
|
- Test currency code mappings
|
||
|
|
- Test securities identifier mappings
|
||
|
|
- Test LEI mappings
|
||
|
|
- Test payment code mappings
|
||
|
|
- **Success Criteria**: ISO integration tested
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 17: Enterprise Security (1 task)
|
||
|
|
|
||
|
|
#### Task 17.1: Security Audit for Diamond Architecture
|
||
|
|
- **Priority**: 🟡 High
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 4-6 weeks
|
||
|
|
- **Dependencies**: All implementation tasks
|
||
|
|
- **Description**:
|
||
|
|
- Professional security audit
|
||
|
|
- Access control review
|
||
|
|
- Upgrade mechanism review
|
||
|
|
- Facet security review
|
||
|
|
- Compliance review
|
||
|
|
- **Success Criteria**: Security audit completed and issues resolved
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
### Category 18: Enterprise Documentation (1 task)
|
||
|
|
|
||
|
|
#### Task 18.1: Document Enterprise Architecture
|
||
|
|
- **Priority**: 🟢 Medium
|
||
|
|
- **Status**: Pending
|
||
|
|
- **Estimated Time**: 2-3 weeks
|
||
|
|
- **Dependencies**: All implementation tasks
|
||
|
|
- **Description**:
|
||
|
|
- Document Diamond structure
|
||
|
|
- Document all facets
|
||
|
|
- Document ISO integration
|
||
|
|
- Document FireFly integration
|
||
|
|
- Create operational runbooks
|
||
|
|
- **Success Criteria**: Complete documentation
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## 📊 Updated Task Statistics
|
||
|
|
|
||
|
|
### Total Tasks: 41
|
||
|
|
- **Critical**: 12 tasks
|
||
|
|
- **High Priority**: 15 tasks
|
||
|
|
- **Medium Priority**: 14 tasks
|
||
|
|
|
||
|
|
### Task Categories
|
||
|
|
- CCIPLogger Deployment: 2 tasks
|
||
|
|
- Chain-138 Infrastructure: 2 tasks
|
||
|
|
- Chain-138 Bridge Deployment: 2 tasks
|
||
|
|
- Bridge Configuration: 3 tasks
|
||
|
|
- Testing: 5 tasks
|
||
|
|
- Monitoring: 6 tasks
|
||
|
|
- Security: 1 task
|
||
|
|
- Documentation: 1 task
|
||
|
|
- Optimization: 1 task
|
||
|
|
- **Enterprise Diamond: 2 tasks**
|
||
|
|
- **Enterprise ERC Standards: 6 tasks**
|
||
|
|
- **Enterprise ISO Standards: 2 tasks**
|
||
|
|
- **Enterprise FireFly: 2 tasks**
|
||
|
|
- **Enterprise Bridge/Vault: 2 tasks**
|
||
|
|
- **Enterprise Governance: 1 task**
|
||
|
|
- **Enterprise Testing: 3 tasks**
|
||
|
|
- **Enterprise Security: 1 task**
|
||
|
|
- **Enterprise Documentation: 1 task**
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## 🎯 Enterprise Architecture Priority
|
||
|
|
|
||
|
|
### Phase 1: Foundation (Critical)
|
||
|
|
1. Design Diamond architecture
|
||
|
|
2. Implement Diamond core
|
||
|
|
3. Deploy FireFly infrastructure
|
||
|
|
4. Implement FireFly integration
|
||
|
|
5. Implement basic facets (ERC-20, ERC-721)
|
||
|
|
|
||
|
|
### Phase 2: Financial Standards (High Priority)
|
||
|
|
6. Implement ERC-1400/1404
|
||
|
|
7. Implement ERC-3475
|
||
|
|
8. Implement ERC-3643
|
||
|
|
9. Implement ERC-4626
|
||
|
|
10. Implement ISO Registry
|
||
|
|
|
||
|
|
### Phase 3: Integration (High Priority)
|
||
|
|
11. Set up ISO mappings
|
||
|
|
12. Implement Bridge module
|
||
|
|
13. Test all facets
|
||
|
|
14. Test FireFly integration
|
||
|
|
|
||
|
|
### Phase 4: Advanced (Medium Priority)
|
||
|
|
15. Implement Governance module
|
||
|
|
16. Implement Vault module
|
||
|
|
17. Security audit
|
||
|
|
18. Documentation
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## ⏱️ Updated Timeline
|
||
|
|
|
||
|
|
### Enterprise Architecture Timeline
|
||
|
|
- **Phase 1 (Foundation)**: 4-6 weeks
|
||
|
|
- **Phase 2 (Financial Standards)**: 6-8 weeks
|
||
|
|
- **Phase 3 (Integration)**: 4-6 weeks
|
||
|
|
- **Phase 4 (Advanced)**: 4-6 weeks
|
||
|
|
- **Total**: 18-26 weeks
|
||
|
|
|
||
|
|
### Combined Timeline (Original + Enterprise)
|
||
|
|
- **Original Tasks**: 3-4 weeks
|
||
|
|
- **Enterprise Architecture**: 18-26 weeks
|
||
|
|
- **Total Project**: 21-30 weeks (5-7.5 months)
|