# Disaster Recovery Procedures ## Overview This document outlines procedures for disaster recovery and business continuity for the DBIS Core Lite payment system. ## Recovery Objectives - **RTO (Recovery Time Objective)**: 4 hours - **RPO (Recovery Point Objective)**: 1 hour (data loss tolerance) ## Backup Strategy ### Database Backups **Full Backup:** - Frequency: Daily at 02:00 UTC - Retention: 30 days - Location: Secure backup storage - Format: Compressed SQL dump **Transaction Log Backups:** - Frequency: Every 15 minutes - Retention: 7 days - Used for point-in-time recovery ### Audit Log Backups - Frequency: Daily - Retention: 10 years (compliance requirement) - Format: CSV export + database dump ### Configuration Backups - All configuration files (env, certificates) backed up daily - Version controlled in secure repository ## Recovery Procedures ### Full System Recovery 1. **Prerequisites:** - Access to backup storage - Database server available - Application server available 2. **Steps:** ```bash # 1. Restore database gunzip < backups/dbis_core_YYYYMMDD.sql.gz | psql $DATABASE_URL # 2. Run migrations npm run migrate # 3. Restore configuration cp backups/.env.production .env # 4. Restore certificates cp -r backups/certs/* ./certs/ # 5. Start application npm start ``` ### Point-in-Time Recovery 1. Restore full backup to recovery server 2. Apply transaction logs up to desired point 3. Verify data integrity 4. Switch traffic to recovered system ### Partial Recovery (Single Table) ```sql -- Restore specific table pg_restore -t payments -d dbis_core backups/dbis_core_YYYYMMDD.dump ``` ## Disaster Scenarios ### Database Server Failure **Procedure:** 1. Identify failure (health check, monitoring alerts) 2. Activate standby database or restore from backup 3. Update connection strings 4. Restart application 5. Verify operations ### Application Server Failure **Procedure:** 1. Deploy application to backup server 2. Update load balancer configuration 3. Verify health checks 4. Monitor for issues ### Network Partition **Procedure:** 1. Identify affected components 2. Route traffic around partition 3. Monitor reconciliation for missed transactions 4. Reconcile when connectivity restored ### Data Corruption **Procedure:** 1. Identify corrupted data 2. Isolate affected records 3. Restore from backup 4. Replay transactions if needed 5. Verify data integrity ## Testing ### Disaster Recovery Testing **Schedule:** - Full DR test: Quarterly - Partial DR test: Monthly - Backup restore test: Weekly **Test Scenarios:** 1. Database server failure 2. Application server failure 3. Network partition 4. Data corruption 5. Complete site failure ## Communication Plan During disaster: 1. Notify technical team immediately 2. Activate on-call engineer 3. Update status page 4. Communicate with stakeholders ## Post-Recovery 1. Document incident 2. Review recovery time and process 3. Update procedures if needed 4. Conduct post-mortem 5. Implement improvements ## Contacts - **Primary On-Call**: [Contact] - **Secondary On-Call**: [Contact] - **Database Team**: [Contact] - **Infrastructure Team**: [Contact]